This is a 74 page detailed summary of the drilling activities of Utah FORGE 16A(78)-32, a highly deviated well completed on February 2nd, 2021, as part of the Utah FORGE project. This well was deviated at 65 degrees from vertical after reaching 6000 feet in depth had a total measured depth of 10,987 feet. The report summarizes the operations, lessons learned, and recommendations for each drilled section of the well.
데이터 정보
연관 데이터
Utah FORGE: Well 16A(78)-32: Summary of Drilling Activities
공공데이터포털
This is a 74 page detailed summary of the drilling activities of Utah FORGE 16A(78)-32, a highly deviated well completed on February 2nd, 2021, as part of the Utah FORGE project. This well was deviated at 65 degrees from vertical after reaching 6000 feet in depth had a total measured depth of 10,987 feet. The report summarizes the operations, lessons learned, and recommendations for each drilled section of the well.
Utah FORGE: Well 16A(78)-32 Drilling Data
공공데이터포털
This dataset includes survey data, drilling data, daily reports, summaries of daily operations, and rig photos from the drilling of Utah FORGE well 16A(78)-32, which is a highly deviated deep well. It was completed 60 days ahead of schedule. Rig move in began 10/22/2020 and drilling commenced on 10/30/2020, and total depth was reached on 12/18/2020. Drilling was followed by a diagnostic fracture injection test (DFIT), logging, and circulating casing. The rig was released on 1/12/2021. The upper part of the well was drilled vertically through approximately 4,700 feet of sediments before penetrating into high strength, crystalline granite. The well was deviated at a 65 degree angle from vertical after reaching a depth of 6,000 ft. This angle was maintained for the remainder of the well's trajectory. The well ultimately reached a true vertical depth of 8,559 feet, and a total measured depth of 10,987 feet. Preliminary measurements indicate temperatures at the "toe" of the well will exceed 442 degrees F (228 degrees C). Approximately 74 ft of core of the granitic and metamorphic rocks that will form the FORGE reservoir was also recovered.
Utah FORGE: Well 16A(78)-32 Drilling Data
공공데이터포털
This dataset includes survey data, drilling data, daily reports, summaries of daily operations, and rig photos from the drilling of Utah FORGE well 16A(78)-32, which is a highly deviated deep well. It was completed 60 days ahead of schedule. Rig move in began 10/22/2020 and drilling commenced on 10/30/2020, and total depth was reached on 12/18/2020. Drilling was followed by a diagnostic fracture injection test (DFIT), logging, and circulating casing. The rig was released on 1/12/2021. The upper part of the well was drilled vertically through approximately 4,700 feet of sediments before penetrating into high strength, crystalline granite. The well was deviated at a 65 degree angle from vertical after reaching a depth of 6,000 ft. This angle was maintained for the remainder of the well's trajectory. The well ultimately reached a true vertical depth of 8,559 feet, and a total measured depth of 10,987 feet. Preliminary measurements indicate temperatures at the "toe" of the well will exceed 442 degrees F (228 degrees C). Approximately 74 ft of core of the granitic and metamorphic rocks that will form the FORGE reservoir was also recovered.
Utah FORGE: Well 16B(78)-32 Drilling Data
공공데이터포털
This drilling data for Utah FORGE well 16B(78)-32 include a well survey, core summary, mud and mud temperature logs, daily reports of the drilling process, and additional data from the Pason oil and gas company. Well 16B(78)-32 serves as the production well for reservoir creation, fluid circulation, and demonstration of heat extraction for the FORGE project. It has been drilled as a doublet approximately 300 feet parallel to and above the injection well 16A(78)-32. The proposed total depth was 10,658 feet, which was exceeded. Spudding began on April 26th, 2023. As of June 20th, 2023, the total depth measured 10,947 feet and the vertical depth measured 8,357 feet. Drilling included the trial use of insulated drill pipe (IDP) from Eavor Technologies, which was considered a success. IDP restricts counter-current heat transfer between drilling fluid inside the drill string and hotter returning fluid in the annulus, thereby ensuring the bottomhole assembly (BHA) remains submerged in cool fluid. Eavor rented 350 joints of IDP to FORGE which were run in two consecutive BHAs at the well. The results of this trial are included here.
Utah FORGE: Well 16A(78)-32 Logs
공공데이터포털
This dataset contains all well logs from Utah FORGE well 16A(78)-32. This includes the mud log, Sanvean Technologies logs, and Schlumberger logs. Please see the file descriptions below for information about each log.
Utah FORGE: Well 16A(78)-32 Logs
공공데이터포털
This dataset contains all well logs from Utah FORGE well 16A(78)-32. This includes the mud log, Sanvean Technologies logs, and Schlumberger logs. Please see the file descriptions below for information about each log.
Utah FORGE: Well 16A(78)-32 Planned Trajectory
공공데이터포털
This submission includes an Excel spreadsheet containing the Utah FORGE deep well 16A(78)-32 planned trajectory including UTM coordinates, elevations, and depths from the well head to the toe. This proposed new injection well is expected to descend vertically to a depth of approximately 1810 m and then extend laterally at an angle to a MD of approximately 3290 m and a maximum vertical depth of approximately 2584 m. There is approximately 1500 m of basin fill at the well head, and less than that above the simulation region with the targeted reservoir region fully enclosed in granitoid basement. The last 60 m of the well will be open hole. Drilling is planned for October 2020. Please direct questions to the Utah FORGE team: utahforge@utah.edu and check the Utah FORGE website: https://utahforge.com after October for more information.
Utah FORGE: Video of Utah FORGE Drilling Planning for Production Well 16B(78)-32
공공데이터포털
This is a YouTube video containing the specifics of well planning for Utah FORGE 16B(78)-32. This well will be drilled as a doublet approximately 300 feet parallel to and above 16A(78)-32 and will be drilled between approximately April 15th and July 17th 2023.
Utah FORGE: Video of Utah FORGE Drilling Planning for Production Well 16B(78)-32
공공데이터포털
This is a YouTube video containing the specifics of well planning for Utah FORGE 16B(78)-32. This well will be drilled as a doublet approximately 300 feet parallel to and above 16A(78)-32 and will be drilled between approximately April 15th and July 17th 2023.
Utah FORGE: Wells 16A(78)-32 and 16B(78)-32 Stimulation Program Report - May 2024
공공데이터포털
This dataset consists of a comprehensive report documenting the stimulation program conducted in May 2024 on Utah FORGE wells 16A(78)-32 and 16B(78)-32. It includes detailed accounts of operational and scientific objectives, stimulation methodologies, and testing outcomes. The report describes the hydraulic fracturing activities, equipment setups, proppant and fluid usage, and the execution of a nine-hour circulation test. It also includes observations from seismic and fiber optic monitoring systems, providing data on microseismic activity and fracture propagation. Detailed parameters for each stimulation stage are provided, alongside operational challenges and solutions. The dataset includes analyses of injection and production rates, well temperatures, and pressure data, supported by graphical illustrations and logs.